Material allocation

3 replies [Last post]
ROHIT RANGNEKAR
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 29 May 2009
Posts: 47
Groups: None
Dear All,

How can I assign a material to an activity ? I have tried by making material as a resource but I am unable to choose options from unit of measure tab which is making material as labor resource. How can I overcome this or there is any another way to assign material to activity?

Regards,

Replies

Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Rohit,

Go to Resources --> Units & Prices tab, under the Price / Unit Settings, input the any number you want to.

Regards,

Arnold
ROHIT RANGNEKAR
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 29 May 2009
Posts: 47
Groups: None
Dear sir,

How can i assign price to it?

Regards
Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Rohit,

Create first the resource in the resources workspace after creating, change the resource type into material, so that you can assign the unit of measure. Then assign it to your activities.

Regards,