Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Negative Float on Milestone?

12 replies [Last post]
Victoria Tan
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 11
Groups: None
Hi Guys,
I have a milestone in my P5 schedule which finish date is correct as planned. However, the milestones and all of its predecessors (20#) are showing negative float, while all of its successors are showing positive float.

There are no constraints in the logic path, no must finish by date on the project, and I am scheduling using progress override.

Any ideas please?
Vicky

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Look for external relationships to activities outside of your current schedule. Add the Projects column to your relationship tabs. This may show you something. Good luck!
David Podmore
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 26 Apr 2006
Posts: 74
Groups: None
Hi Victoria,

Still having probs? I have found that on very rare occasions that some actual data once entered and then removed (for whatever reason) can remain in the database despite appearing not to. If the job is not too onerous I would be tempted to make an XER of where you are now so you can go back and then take off progress, task by task, up the logic stream, recalculating after each. You may find the oddity this way.
If you do find it, note the task details and delete it. Add it back in as before and retrace the progress back to now. A hassle but no one said detective work is easy...

David
Satya Narayana
User offline. Last seen 10 years 17 weeks ago. Offline
Joined: 29 Apr 2008
Posts: 47
Thats really tricky
Victoria Tan
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 11
Groups: None
Hi Sat,

Yes some predecessors have actual dates but I am using progress override?

I changed milestone to finish but float still the same.

Looks like a long nite for me...boss said negative float cannot lah! :-)

Cheers
Vicky
Satya Narayana
User offline. Last seen 10 years 17 weeks ago. Offline
Joined: 29 Apr 2008
Posts: 47
check if some actual date was entered in any of the activity
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
i’m sure there are invalid relationships as well in the schedule log, try changing it to finish milestone and see what happens, or you can add another milestone (in this case you need to change the logic).
Victoria Tan
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 11
Groups: None
Hi Anoon,

It is a start milestone.

Cheers
Vicky
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
is it a finish milestone or a start milestone?
Victoria Tan
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 11
Groups: None
Thanks again Oliver,

I am using P5 as Standalone.

Any other suggestions?

Cheers
Vicky
Oliver Melling
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Try pressing F5 to refresh the data as someone on the same database might have added something whilst you’ve working.
Victoria Tan
User offline. Last seen 12 years 26 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 11
Groups: None
Checked already Oliver.

I’m tearing my hair out here...

Please anyone? I’m fairly new to P5 but have not come across this in P3 before.

Thanks
Vicky

Oliver Melling
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Double check that you don’t have any constraints on the milestone?