Finish On or Before

7 replies [Last post]
Alexandre Faulx-B...
User offline. Last seen 1 year 50 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355
Hi there,
I would like to put a schedule constraint on the last task of my project; this task being a milestone, I cannot use Expected Finish; when I use Finish On or Before and put a date sooner than the Planned Finish date, PM5 shortens the project duration by the difference between Finish On or Before and Planned Finish.
How can I get PM5 to calculate and display a negative float instead?
Have a good week-end, and thanks all for your help
Alexandre

Replies

Pradeep Kumar Mah...
User offline. Last seen 4 years 50 weeks ago. Offline
Joined: 19 Apr 2004
Posts: 11
Hi Alex,

Thanks for the notes.

In general, as a planning engineer one must review the performance of the project and see internally if any activity in the project schedule is creating negative float. This is to generate an alarm for the down the line construction team to convey an urgency or expediting the work progress. This is to be used as a project management technique in construction management.

But when the schedule is submitted to the client,as a monthly update, the constraint applied to the end date must be taken out and schedule should be allowed to run on the basis of a free flow logic.

Now taking the discussion further and to share my views with you, I would say that, the imposition of constraint in a schedule to be kept as minimum as possible (by saying so I do not specify a number) but the usage of constraints should be as minimum as possible otherwise it will be something like the absuses of scheduling techniques even though software does not limit us on the number of usage. As a matter of good practice, this should be in vogue.

Anyway.
Thanks.

PK.
Muscat
Pradeep Kumar Mah...
User offline. Last seen 4 years 50 weeks ago. Offline
Joined: 19 Apr 2004
Posts: 11
Hi All,

I believe imposing a Constraint date on the Finish Milestone is not a good practice, as you all know that, this would generate negative float.
However the schedule end date should be a free floating type which would be driven by the logic built into it and depending the progress % of its predecessors.
However if the imposition of the Must Finish constraint is purely for Crashing purpose or for a producing recovery plan , then the slippage duration must be recovered from the activities in Longest/ Critical Path to bring back the schedule to the Baseline Finish date.

Cheers.
Keep Planning.

PK.
Patricia Le Clainche
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
Bonjour Alexandre,

Could you please tell us more about options you have. As far as I am concerned, I put a Primary Constraint "Finish On or Before" on all my Finish Milestones. And each time the predecessor(s) is(are) delayed, I get the "desired" negative float.

In some specific cases, I have some milestones without any predecessor and I use both Primary & Secondary constraints : the first one with "Finish On or after" and the second one with "Finish On or Before". Therefore, if the milestone is delayed, I can show a negative float , by changing the Primary contraint date.

I hope it helps.
Cordialement.
Patricia
K D
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi Alex.
I tested your constrained situation,applying constrain on finish milestone, on my PC and Primavera gave a negative float as usual.
You said in your system ,it shorten duration. Could you tell us which activity in project does Primavera shorten duration? Is it the next to the last one?
Have you upgrade Primavera to the lastest SP : SP4?

Thanks
Rodel Marasigan
User offline. Last seen 4 hours 54 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Alexandre,

You can use Must Finish By as a constrain under Enterprise-> Project then select the project that you wanted to constrain and click the Date tab. Enter an earlier date on “Must Finish By” text box and P5 will show it as negative float.

Regards,
Rodel