Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration Types

4 replies [Last post]
Nitin Naik
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 1 Feb 2005
Posts: 27
Groups: None
Hi,

Currently there are four Duration types which you can assign to an activity.

Apparently it works around the following equation -

Duration X Resource Units/Time = Units

I am looking for some real life examples to easily demonstrate different duration types and its use.

Please share your thoughts and examples on this topic.

Cheers

Nitin

Replies

John Murray
User offline. Last seen 17 years 2 weeks ago. Offline
Joined: 15 Apr 2007
Posts: 4
Groups: None
Some example uses for the Duration Types…

"Fixed Units/Time" – Use against a Level of Effort eg Project Manager over the duration of the Project.


"Fixed Duration & Units/Time" – Typical Construction activity, remaining duration is forecast then this activity type gives the required units/resources per remaining time period (Projecting remaining required project resources to meet schedule), productivity may also need to be considered.


"Fixed Units" – Use for High Level Schedule (perhaps Owners schedule or EPC study phase, Level 1, 2) to assist in determining the overall duration of a program by manually leveling (shrinking and stretching) activities to meet a perceived / achievable resource limit (base resource data is a high level estimate of resources).


"fixed duration and units" - Typical Shutdown / Turnaround activity, when you want to know what it will take to make sure the work is completed on time, this good for re-assessing resource requirement (resource leveling) when a shutdown is in progress.

Many arguments can be put for and against the above; however they are legitimate uses and would be best discussed with Primavera for your particular industry, also I have not looked, but I am sure many example exist on the Primavera Knowledge Base http://www.primavera.com/customer/index.asp

Best Regards
John
Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
it’s all linear! use only fixed units!
Peter Nicol
User offline. Last seen 17 years 3 weeks ago. Offline
Joined: 11 Apr 2007
Posts: 5
Groups: None
This might help explain things...

The duration type affects the following 3 items:

"Duration"
"Units/Time"
"Units"

Whichever duration type you select will select which one of these 3 items change first. Each duration means the following:

"Fixed Units/Time" - duration changes first and the "units" change 2nd. ie. if you change the duration of an activity, the units will change accordingly (based upon the units/time already set).

"Fixed Duration & Units/Time" - "units" changes first and then duration changes 2nd.

"Fixed Units" - duration changes first and units/time changes 2nd.

"fixed duration and units" - units/time changes first and units changes 2nd.

hope this makes sense

-Pete
Aydin Valiyev
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 28 Mar 2005
Posts: 6
Groups: None
Hi Nitin,

You can compare with P3 autocost rules. If you in P3
1. Link RD to % complete it will give you in P5 duration type
2. Unlink RD to % complete it will give you in P5 physical type

I didn’t reach to Units yet.:)

Cheers,
Aydin