Resource Profile Selection

2 replies [Last post]
Mike Parsons
User offline. Last seen 18 years 11 weeks ago. Offline
Joined: 13 Dec 2005
Posts: 6
Groups: None
I remember being able to select and display several resources that would display "stacked" in various colors in the resource profile/table in P3. I can’t seem to find it in P3ec. What I am really after is being able to print a schedule showing all resources required in graphic form. My schedule has about 12 resources. Any ideas? Thanks.

Replies

Mike Parsons
User offline. Last seen 18 years 11 weeks ago. Offline
Joined: 13 Dec 2005
Posts: 6
Groups: None
Thank you.
Kevin Button
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Mike

With the Resource Usage Profile displayed, right click on the profile and select ’Stacked Histogram’. Then right click again and select ’Resource Usage Profile Options’ and here you build your filters for the various resources and colours in the stack. You wil also need to right click and uncheck the ’Show All Projects’ option if yo want to display resource usage for the open project only.

Cheers