Import-Export from P3 to P6 and Vice Versa

1 reply [Last post]
Ariel Malibiran
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 6 Mar 2009
Posts: 54

Hi Guys!

 

need your urgent help please!

I have my schedule prepared in P3. I prepared the detailed schedule in P6 by importing it. After completing the detailed schedule, I exported it back to P3 version.

As I open the P3 file of my detailed schedule, the logic/relationships is no longer working. Even if you change a relationship, it does not recalculate.

 

 

Please help me asap.

 

Thanks,

 

Ariel

Replies

Ariel Malibiran
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 6 Mar 2009
Posts: 54

got answer to my question...by re-selecting the Project Start date at Project Overview then re-scheduling(not shortcut/F9) re-specifying the data date...this is because P6 has time in calendar/consider time in the calculation i guess.