actual curve in p3 from tabular report

1 reply [Last post]
Yaser A. Al-Bustanji
User offline. Last seen 1 year 11 weeks ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

 

Dears,

I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early dates and one for late dates so i have tow different actual curve, why this problem appears and how i can solve it

 

Sorry for my bad language

 

Regards 

Replies

Rafael Davila
User offline. Last seen 6 hours 20 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical.

Plan = Remaining Work after DD