Relationships Help required

1 reply [Last post]
Thomas Nicholson
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 4 Oct 2006
Posts: 87
Groups: None

Hi there,

I wonder if someone could remind me how I could sort this out?

I have 5 activities A, B, C, D & E starting at different times from now until April, I have them all linked into another activity (F)which I need to start with the earliest date of the preceeding activities.  However the dates (A-E) start could change and I want  activity (F) to reflect the earliest start of them all as and when. I've tried linking them via SS and FS and FF but none make (F) start date equal the earliest date of A-E.

Any ideas?

thanks all.

Thom

Replies

Olubukola Fasoyin
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 27

Hi Tom,

If I understand your question. Goto Task Type from activity form for activity F and make Type= Hammock while maintianing your SS relationship to each of A-E, and FF to each A-E.

But Note that F  will have no effect on the schedule but will reflect what you want to see.

Regards

 

Bukola