Adding more activities to base line schedule

2 replies [Last post]
Radhakrishnan Nair
User offline. Last seen 6 years 5 weeks ago. Offline
Joined: 4 Jan 2009
Posts: 20
Groups: None
Dear All,

Please help me with the following. We have a project just started. It’s base line is approved and the first baseline updation is done. Now we have been awarded with some more additional works( which was an optional item earlier). How to include these in the schedule. Do we have to modify the WBS. Can we do it in the approved baseline schedule. This additional works have a time impact also. Apprecite the steps involved in this. pls mail to krishnan_uae@yahoo.com

Regards,
Krishnan

Replies

Waseem Saber
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 1 Dec 2004
Posts: 63
Groups: None
Agree with Gary,

it is imperative that you rebaseline by including this new scope and this should be submitted for acceptance and then this will become your new baseline.

wondering what are the conditions of the contract...?

cheers

Waseem Saber
Gary Whitehead
User offline. Last seen 6 years 2 weeks ago. Offline
1) Copy ther approved baseline schedule,
2) update WBS, activitites, resources, schedule, logic, etc to reflect additional works
3) Make sure you understand & can defend any impact on the schedule for original scope arrising from the addition of the new works.
4) Issue new baseline schedule, manpower loading, cashflow forecasts, etc for approval