Report to show actual vs target W/O resources

2 replies [Last post]
Jason Audette
User offline. Last seen 14 years 2 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 5
Groups: None
All,

I am trying to produce a report that shows actual vs target %complete. My schedules are NOT resource loaded. How do I show, in a graph, that either we are on schedule, behind or ahead? I know I cannot produce a S-curve without resources. It was mentioned to set up resource called time and use the durations as amounts but I am unclear on how to do that. Any help would be great.

Replies

A D
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
define a resource and then put BQ=OD using global change

and then plot the graph
mimoune djouallah
User offline. Last seen 5 years 47 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
hi

just assign a resource to all activities " let’s call it TIME for simplification" with 1 as units per day, then you can generate your S curve

HTH