Pacifico Pallasigui
User offline. Last seen 13 years 3 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
Planners,


Anybody have encountered this problem in updating, I have an activity to update resourced and cost loaded , I have inputted the actual start but when I input the % complete it does not accept the data I input it goes back to 0%.

Thank You

Pacifico

Replies

osama Eltantawy
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 25 Jan 2009
Posts: 12
Groups: None
when the resource is a driving resource P3 calculate the percent complete based on resource % complete rather than activity % complete. so, you have to make the resource is not driving and update the activity % complete OR update the driving resource % complete and it will be reflected on the activity % complete.

Osama,
Pacifico Pallasigui
User offline. Last seen 13 years 3 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None

I have solved it in the resource tab I uncheck the driving of all the resources and the % appeared ..Can anybody know whats the reason for this??
Jan Richard Noble
User offline. Last seen 14 years 33 weeks ago. Offline
Joined: 14 Nov 2005
Posts: 18
Groups: None
Hi Pacifico,

Try to copy the file and work with the copied one. it might be corrupted...

regards,