how to make p3 not change my Budget quantity ?

2 replies [Last post]
mimoune djouallah
User offline. Last seen 5 years 49 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
hi planners.

when i update my planning ( actual start date, actual to date and % complete), sometimes the budget change ?
is there an option in p3 to fix the initial budget ?

thanks

Replies

Mohammed Mujtaba
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 23
If u run the global change u can get the same BQ..
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
go to your target project