Master Construction Schedule Advice

2 replies [Last post]
Jason Audette
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 5
Groups: None
I am currently starting a construction project that is going to have many different subcontractors and with different schedule formats. There will even be some that don’t even have a schedule for me. Any advice on how I should go about building a master construction schedule in P3 format?

Replies

Imran Yousuf
User offline. Last seen 6 years 31 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 6
Sajid, can u explain how to use the "SubProjects"
Sajid Balma
User offline. Last seen 14 years 2 days ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
Use of subprojects is more advantageous. Subprojects will be the Work Packages of different contractors.