what is impact on schedule using negative Lag

2 replies [Last post]
salauddin mohamme...
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 10 Dec 2005
Posts: 4
Groups: None
Dear all,

pls anybody adivse me why we can’t use negative lag in the schedule, The client or consultant advising no to use. Why? what is the reason.

I beleive that if we didn’t use negative lag, the schedule is not properly on critical path, hence, several activities with total float more than zero or one.

Replies

Brad Richey
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 22 May 2008
Posts: 20
Groups: None
If you change the relations from FS with -ve lag to SS with +ve lag be sure to include a FF relationship between the same two items if you do not you may be finishing the successor before the predecessor completes.

Ahmad saeed
User offline. Last seen 15 years 33 weeks ago. Offline
Joined: 29 Jun 2008
Posts: 5
Groups: None
Hi Salauddin,

Using negative lags in the relationship has no effect on the schedule.

you can change the relations from FS with -ve lag to SS with +ve lag.

Hope that this will help.