difference between ACWP & BCWP

5 replies [Last post]
Sinan Fahmi
User offline. Last seen 8 years 44 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 68
Groups: None
hi planners,
can you explain to me the difference between ACWP & BCWP.

THANX

Replies

Alastair Morrison
User offline. Last seen 4 years 46 weeks ago. Offline
Joined: 30 Jan 2007
Posts: 48
Groups: None

BCWP = Budgect Cost Of Work performed (more commenly described as Earned Value and this is calculated very simply by using the percentage reported for work done for achieving either hours or value of the activity being progressed or measured.

 

Ie Task 1 has a budget of £10,000 and will take 100 manhours to complete so if you have claimed you are 50% complete then you have achievdd 50% of the cost and effort . £5000 & 50hrs respectively

ACWP = Actual Cost of Work performed  which as it states the "actual cost used and the actual hours burned.

Ie if you have spent £4000 and burned 40 hours then that is what you report for ACWP (40%)

 

In this instance depending on your baseline data the project looks healthy

You have achieved more than you have expended , if the Planned Cost of Work Performed indicates you are ahead at this point , use S Curves to establish this.

Waseem Masalma
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 13 Jul 2015
Posts: 5

Thanks For Great Explanation

Sinan Fahmi
User offline. Last seen 8 years 44 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 68
Groups: None
thanx alot my friends for this great explain
Karim Mounir
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi sinan,

ACWP: Actual cost for work performed
What is the actual cost incurred for the work completed?
- If u’ve a task which has a budget of $1000, u completed 70% of this task, then the ACWP will be the actual cost that u incurred to complete this 70%.

BCWP: Budgeted cost for work performed (Earned Value or EV)
What is the estimated value of the work actually completed?
- If u’ve a task which has a budget of $1000, u completed 70% of this task then the BCWP will be equal to 70%x1000 (one of the methods in calculating EV) regardless of how much this task has actually cost.
Joe Hellenbrand
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 13 Sep 2007
Posts: 19
P3 help defines ACWP as Actual costs incurred for work performed - what it really cost you to perform that work. it is independent of %complete and budgeted costs. if you had to pay for extra concrete or OT so be it those are reflected here

BCWP is what it should have cost you according to your budget to perform that work. say you have completed 10% of a $1000 activity the BCWP should be $100 (0.1 X $1000 = $100)