Primavera Project Planner - P3 Member for 22 years 6 months Member for 22 years 6 months Submitted by DATTATREYA PADHARTHI on Fri, 2007-08-17 21:53 Permalink RE: Export P3 file to Excel and import Excel to P3 Amit, If you are using Office 2003,Export as *.dbf file , open in excel modify, save as dbf with errors. Import back in P3.(Check for number of activities during this process. If using Office 2007, export as dbf, open in MS access, modify/change & save as dbf & import back. Cheers Dattatreya Log in or register to post comments
Member for 22 years 6 months Member for 22 years 6 months Submitted by DATTATREYA PADHARTHI on Fri, 2007-08-17 21:53 Permalink RE: Export P3 file to Excel and import Excel to P3 Amit, If you are using Office 2003,Export as *.dbf file , open in excel modify, save as dbf with errors. Import back in P3.(Check for number of activities during this process. If using Office 2007, export as dbf, open in MS access, modify/change & save as dbf & import back. Cheers Dattatreya
Member for
22 years 6 monthsRE: Export P3 file to Excel and import Excel to P3
Amit,
If you are using Office 2003,Export as *.dbf file , open in excel modify, save as dbf with errors.
Import back in P3.(Check for number of activities during this process.
If using Office 2007, export as dbf, open in MS access, modify/change & save as dbf & import back.
Cheers