MPP to P3

1 reply [Last post]
RAIEZ MOIDEEN
User offline. Last seen 13 years 38 weeks ago. Offline
Joined: 18 Jun 2007
Posts: 3
Groups: None
Its not working when I assign relations to the activity with activity type WBS, just as assigning relations to main tasks in MPP. Please tell me a solution.
Or else pls suggest me a way to show main tasks and sub tasks as in MPP, where a main task can have relation with with other main tasks or sub tasks in other main tasks.

Replies

Paul Harris
User offline. Last seen 2 years 12 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
A WBS activity spans the duration of all activities with the same WBS code. It is not intended to assign relationships to a WBS activity.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au