P3 3.0 Calendar

3 replies [Last post]
Ahmed Syed
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 21
Groups: None
Dears

I have just re-installed P3 on my other system. But, interestingly I am getting only the months and years in calenders....no dates. Is it a corrupted installation or am I missing something? I would prefer to replace the corrupted file rather re-installing P3 as I moved my files over here. Any suggestions?????

Ahmed

Replies

Ahmed Syed
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 21
Groups: None
Thanks Ashraf and Pranab for your help.

So Stupid of me. When I copied my Project I did not put any attention to Planning Unit details that was set on Months. So, I had to copied it back with Planning Unit as DAYS and it is back to normal.

CHEERS
Ashraf Jahangeer
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Ahmed,

Bit strage, if it is for the running projects that you are working on. However if this problem is with new project then try to transfer calendar from the existing project.

Regards,

Ashraf
Pranab Kumar Deb
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Hello Ahmed,
I feel this will restore the issue
Double click the Date Line( Time Scale ) , the time scale bar will pop > click calender dates and minimum time unit days
regards
deb