multiuser simultaneous edit in a single project

2 replies [Last post]
Keyel Isorena
User offline. Last seen 3 years 29 weeks ago. Offline
Joined: 31 Oct 2006
Posts: 44
just wanted to know if it possible to have 2 or more users edit a single project save on a network folder, if it is, how? thanx in advance

Replies

Alex Wong
User offline. Last seen 12 years 12 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
the only restriction is you cannot edit the same activity at the same time

Good Luck

Alex
Jose Frade
User offline. Last seen 4 years 15 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hello,
Yes it is possible (even more users). For that you need:
1. To have the project as multiuser.
2. To have enough licence numbers available (at least two for your example of two planners) to open Primavera for boths planners.
3. None of the users can open the project as exclusive.

With the above you can open the projects with as many licenses as you have.

BR
JMFrade