Average of all resources

1 reply [Last post]
Ijaz Ahmad
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hi Guys,
Can you please help me in how to find the average manpower in P3 for the whole project, if I have different resources?
Thanks
Ijaz

Replies

Alex Wong
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Hi Ijaz

to do that you can use the resource layout, in the display options you select hrs only resouces
then divid it by 8 or what every no of hr per day.
Then in the time scale select you want your average by months or day or week or year.

then in the histogram it will display your average manpower

Good Luck

Alex