Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

MAking Additonal progress Bar...

1 reply [Last post]
Von Ryan Gajo
User offline. Last seen 18 years 39 weeks ago. Offline
Joined: 6 Dec 2006
Posts: 4
Groups: None
How to make an additonal progress bar below the schedule bar... updating it without affecting the Schedule bar above it...thanks and More Power..

Replies

Alex Wong
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS

Create a copy of exisiting schedule

Make it your target schedule
Display your target bar
Modify your target schedule or Current schedule that way the other wont change. Normally you modify your current schedule and maintain the target as a baseline

Good Luck