TIP - >Negativ Resources

No replies
Hannes de Bruyne
User offline. Last seen 2 years 50 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
Sometimes negativ resources are needed e.g. to make a material-balance (Excavation / Fill). It is not possible to write a negative figure into Budgeted Quantities BUT if you write a possitive figure and than changes the units per day to a negativ figure you will have a negativ resource!