Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Quick Tip: Assign Same Resources to Multiple Activities in P6

1 reply [Last post]
Jerome Odeh
User offline. Last seen 1 week 4 days ago. Offline
Joined: 19 Jan 2004
Posts: 102

Earlier this week someone asked me if they could perform a Fill Down with resources in P6 and when I said no, the next question was is there a way to quickly assign same resources to multiple activities? This quick tip outlines steps that answer this question.

https://goo.gl/ZBG4va

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

select ALL activites then rigth click and select assign then select resources then select your resource