Quick Tip: Assign Same Resources to Multiple Activities in P6

1 reply [Last post]
Jerome Odeh
User offline. Last seen 6 days 15 hours ago. Offline
Joined: 19 Jan 2004
Posts: 108

Earlier this week someone asked me if they could perform a Fill Down with resources in P6 and when I said no, the next question was is there a way to quickly assign same resources to multiple activities? This quick tip outlines steps that answer this question.

https://goo.gl/ZBG4va

Replies

Zoltan Palffy
User offline. Last seen 15 weeks 12 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

select ALL activites then rigth click and select assign then select resources then select your resource