Bogus EF dates...

3 replies [Last post]
David Andreotti
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 6 Jul 2005
Posts: 47
Groups: None
I have a started activity, with a remaining duration. I’ve broken the predecessor and successor ties, rescheduled, and am still getting an early finish that does not come from the remaining duration. I’ve run PFXW, recalced many times, etc. Help??

angant

Replies

Sukumaran Subaram...
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Go to Project Overview > check Project Must Finish By. If you imposed any finish date constraint, remove it and re-calculate the schedule.

Regards.
David Andreotti
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 6 Jul 2005
Posts: 47
Groups: None
No, I checked all that.

It turned out to be a topic activity that had a predecessor! I ran the no-topic utility, and organized the schedule in suretrak in outline mode, then outdented everything. Now my RD is driving my EF.
Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Do you have an Expected Finish constraint posted for that activity?