Primavera P6 Answers

2 replies [Last post]
SSS SSS
User offline. Last seen 40 weeks 4 days ago. Offline
Joined: 12 Jan 2012
Posts: 3

Dear All,

How do you make specific activities in p6 start only on Monday irrespective of their predecessor finishing day. I don't want to assign constraints.

Replies

Rafael Davila
User offline. Last seen 8 hours 24 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

2023-07-17-16-34-05 Figure 1

2023-07-17-16-41-36 Figure 2

For a better view hover the figures and click.

Figure 1 shows how with calendar lags can be done. This does not require additional milestone.

Figure 2 shows how with activity lags can be done. This requires an additional intermediate milestone.

The special calendar was created with a very short duration very early on Monday, 0 duration on the remaining days of the week.

Create zero duration activities with calendars that have only one work hour in a week on Monday night.

Add these activities as preceding to your activities that must start on Mondays.

All inbound dependencies to your activities starts must become preceding to created zero duration activities.

This advice will not work if your activities have predecessors to their finish points.