Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

the SOV is usually loosely tied to the Schedule, how do you handle Unit Price items to a lump sum SOV project?

7 replies [Last post]
John Reeves
User offline. Last seen 6 days 20 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

the SOV is usually loosely tied to the Schedule, how do you handle Unit Price items to a lump sum SOV project?  Just add an item and update it each month?  Or base it on an estimated end of project project total?  Are there any special considerations regarding the schedule associated with these items?  Would these require a change order, unless listed a contract contingency?

Replies

Rafael Davila
User offline. Last seen 11 hours 52 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Usually if bid quantity varies by more than 15% unit prices can be re-negotiated and changed via a change order.  This rule is common in LS Contracts with a few unit price items based on an estimated bid quantity similar to Unit Price Contracts.

Variation in Quantity Clauses for Unit Price Contracts

Variation in quantities clauses fairly assign the risk of any changes in the estimated quantity of unit priced items. Thus, large quantity variations will likely require some adjustment to the contract price to prevent severe losses or large profit margins and perhaps an adjustment in contract duration.

Rodel Marasigan
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

SOV and Schedule are usually setup together so you can manage the contract, monitor/track & forecast cost, report against EVM, status the project and keep the project manager up to date. Depending on the total duration of the project, reporting cycle and details of the schedule to setup the appropriate level of the schedule. You have to setup the work breakdown structure (WBS) to make sure all scopes are covered and setup the cost breakdown structure (CBS) as per SOV using account codes. All cost shall be defined in the activity including Preliminaries & expenses belong to the project with the use LOE activities and link to appropriate activities to automate the duration. Direct and Indirect labor shall be defined on labor resource and assigned to activities with appropriate account codes per SOV item. All plants & equipment (hired or owned) shall be defined on non-labor resource shall be assigned to activities with appropriate account codes per SOV item. Same with the purchased materials, equipment, instruments and other purchases belong to the project shall be defined as material resources and assigned to activities with appropriate account code per SOV. Method of measurement will determine the type of resources to be used per SOV item and the rules of credit or productivity steps can be determined whether define as an activity (depending on the duration of the activity) or define as step inside the activity to measure progress.

Ex: if the overall duration of activity for all production step is less than or equal to 1 reporting cycle then you don’t need the production step per activity and use activity steps instead. On this setup, you can report per reporting cycle the SOV status and WBS status of the Project.

In regard to P6 PM accounting tools, P6 Primavera has never been an PM accounting software. P6 never track and issue purchase order/ Job order, does not have function to received purchase materials/ goods and pay supplier or contractor. P6 can manage contract, schedule and forecast cost which totally different from accounting software functions.

John Reeves
User offline. Last seen 6 days 20 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

OK, I see schedule of payment is a different thing.  What is the best way to tie SOV and Schedule which I assume should be a check against the SOV values?  I have been on projects where they print the SOV out of the schedule so that the %'s match the schedule but I think that might be bad because you have to add many line items that require no logic but has to have it plus 10 codes etc.  My motto has been the P6 is a good scheduling tool, but a bad accounting tool.  Remember years ago when there was a sister PM accounting software, with like ball in court etc., is that considered to be in the EPPM version now.  

I think in AEC you can get a combo with Design pre-set and construction pay as built.  

Rodel Marasigan
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Follow up question:

1) G703–1992, Continuation Sheet, provide convenient and complete forms on which the contractor can apply for payment and the architect can certify that payment is due.

2) Unit Cost/ Unit Rate should be agreed by both parties and have been predetermined in advance. The full value might not be fully defined and has no definite end.

John Reeves
User offline. Last seen 6 days 20 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Should unit cost / T&M items be estimated in any of the construction deliverables - ie SOV / CPM schedule etc.?

John Reeves
User offline. Last seen 6 days 20 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

SOV, I have only heard of schedule of payment with something simplified like paying a bank for new house.  Follow up question - can you put G703 on a Pay App document yourself or does G703 mean something like it has been approved by some agency or something?  Is there any good sources to learn about Pay Applications and related issues such as these two?

Rodel Marasigan
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi John,

Are you referring to Schedule Of Values (SOV) or in other terms Schedule Of Payment? In the contract, there should be a Method of Measurement tied up for each line items in SOV whether unit rates or lump sum.