Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2020-06-25 13:22 Permalink if the schedule was always if the schedule was always based on 5 day work week then saying the plan was work 7 days a week. How many days a weeks was he working prior to covid19 ? This should be your basis. I do beleive that a shortage of manpower could and probally did exist but I believe that the EOT should be framed in different manner. Was there ever and original manpower projection ? IF so how does that compaire to the actual manpower on site. The 5 vs 7 working days does not appear to be a correct assumption of the original plan. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2020-06-25 13:22 Permalink if the schedule was always if the schedule was always based on 5 day work week then saying the plan was work 7 days a week. How many days a weeks was he working prior to covid19 ? This should be your basis. I do beleive that a shortage of manpower could and probally did exist but I believe that the EOT should be framed in different manner. Was there ever and original manpower projection ? IF so how does that compaire to the actual manpower on site. The 5 vs 7 working days does not appear to be a correct assumption of the original plan.
Member for
16 years 3 monthsif the schedule was always
if the schedule was always based on 5 day work week then saying the plan was work 7 days a week.
How many days a weeks was he working prior to covid19 ? This should be your basis.
I do beleive that a shortage of manpower could and probally did exist but I believe that the EOT should be framed in different manner.
Was there ever and original manpower projection ? IF so how does that compaire to the actual manpower on site.
The 5 vs 7 working days does not appear to be a correct assumption of the original plan.