EOT - Covid 19

Member for

16 years 3 months
Permalink

if the schedule was always based on 5 day work week then saying the plan was  work 7 days a week.

How many days a weeks was he working prior to covid19 ? This should be your basis.

I do beleive that a shortage of manpower could and probally did exist but I believe that the EOT should be framed in different manner.

Was there ever and original manpower projection ? IF so how does that compaire to the actual manpower on site. 

The 5 vs 7 working days does not appear to be a correct assumption of the original plan.