Contractor has just notified of a claim relating to Covid 19 with a EOT for additional 60 days from the key milestone date. One of the reasons giving by the contractor is that a particular activity which drives the critical path was originally planned for 7 days a week, however with restriction on the number of personnel onsite, the contractor affirm that this particular activity can only be achieved on a 5days working
I have looked through the activity in question and what struck me was that the baseline and the subsequent programme before the delay event did have a 5 days working calendar.
Without going into much effort, can I advise the client to reject the EOT automatically as it does not align with the claim ?
Appreciate any useful advise please.