Adding One Time Expense

2 replies [Last post]
Usman Yasin
User offline. Last seen 3 years 15 weeks ago. Offline
Joined: 27 Mar 2020
Posts: 4
Groups: None

How can i add one time expenses for a project in the total cost that will add up in the total cost but should not distribute in any activity?

Replies

Patrick Mullen
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 15 May 2020
Posts: 19
Groups: None

Hi Usman,

By the sound of it, you just want one activity to equal your total cost on the project. If you don't need to utilize the histograms, then just create a user defined field and call it "Total Expense Cost", and input the value to the activity that you desire.

Regards,

Patrick

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

create a LOE activity 

make the predcessors is a SS relationship with the 1st activity 

make the successor a ff relationship with the last activity in the schedule 

create a resource call it lumpsum

assign the resource to loe activity

add the cost for the project to the resource

then assign a curve to the resource