Fire Proofing for Cables - Schedule

4 replies [Last post]
Kiran Nath
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 4 Mar 2017
Posts: 7
Groups: None

Dear All,

I would like to develop a Schedule for Cable Fire Proofing incl. trays (Intumescent FireProofing cable coating)

Please let me know,

1. What kind of actvities involved in this particlualr work ?

2. What are the Constrains to be started this work ?

Please support me in this regards.....

Replies

Zoltan Palffy
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Kiran Nath
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 4 Mar 2017
Posts: 7
Groups: None

Thank you dear

 

regards,

Kiran Nath
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 4 Mar 2017
Posts: 7
Groups: None

Thank you dear

 

regards,

Zoltan Palffy
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

1st you will need to survey the existing conditions to determine which cables that you want to fire proof

2nd you will have to prepare the immediate area around the cables that you want to fireproof doing things such as putting plastic on other items that you do not want to get the fire-proofing on.

3rd if possible install ventilation in the area where the fire-proofing is beiing performed

4th you will need to rope of the area where the fire-proofing is being sprayed on.   

5th Spraying of the cables is next

6th you will have to clean up any remnants of the fire-proofing that did not adhear

7th remove the plastic that you previously installed

8th remove the ventilation that you previously installed

9th remove the barrier, rope or tape from the area that you previously quarended off

10th done