Primavera P6 - Physical completion % question - I am a beginner

1 reply [Last post]
Toon Blue
User offline. Last seen 5 years 6 weeks ago. Offline
Joined: 17 Dec 2018
Posts: 2
Groups: None

  This is a simple schedule that I have made and I am required to update this schedule every month which is 22 Jan 19.

Please refer to my figure 1 for a simple of this schedule

Now i press the F9 function - scheduling after I have enter physical completion 80% for the buying of materials (A1020). Please refer to the picture below (figure 2).

Somehow this look strange on the gantt chart. Any advise for this?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

did you update the remaining durations ?