Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Critical Path

1 reply [Last post]
ind Vid
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 30 Apr 2016
Posts: 4
Groups: None

Hello Experts,

 

What % of total number of activities in a baseline schedule should ideally be lying on the critical path (TF=0), a number from your extensive experience / best practice would suffice.

 

thank you

 

indra

Replies

Patrick Weaver
User offline. Last seen 1 week 3 days ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

There is no single answer to this - small schedules (low number of activities) will tend to have more activities on the critical path than large schedules, but my heuristic is around 20% is good, below 20% better and knowing the probability of achieving on-time completion is heading 'south' once the percentage gets above 20% (particularly if there are multiple critical paths). 

For more on this see: https://www.mosaicprojects.com.au/WhitePapers/WP1037_Probability.pdf