Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Tips for giving Relationships b/w Activties

No replies
Arslan Shahid
User offline. Last seen 8 years 39 weeks ago. Offline
Joined: 13 May 2015
Posts: 13
Groups: None

I have TWO QUESTIONS regarding following Activities for Coal Fired Power Porject Deployment Activities:

  1. What Relationships should be given to them?
  2. What are the Tips and Tricks should be kept in mind while giving relationships b/w activities in Primavera (when you know the actual sequence between them).

Activity Name

Pre-Bid Activities

Receipt of Consultancy Proposals(Already completed

Evaluation of Technical Proposal & Approval

Opening of Financial Proposal, Evaluation  & Approval by CSC

Negotiation, approval by BoD, Notification and Award

Mobilization and Commencement of Services

Preparation of  Feasibility Study

Review of Feasibility Study by POE, approval  by BOD

EPC Bidding Activities

Appointment of Consultants (Project Management)

Preparation of PQ documents and approval by BOD

Pre-qualification of EPC Contractor

Preparation of Tender level design and bidding documents

Receipt of EPC Bids (Including pre-bid conference and clarifications)

Bid Evaluation

Negotiation, approval of BoD and Award of EPC Contract

Prequalification of coal supplier, invitation of bids, evaluation of bids and CSA

Tariff approval by NEPRA & Generation License

PPA and IA

Financial close

Design Review and Construction Supervision

Mobilization of the EPC Contractor

Design by EPC Contractor and review/approval by consultants

Construction Plus Erection of Plant

Testing, commissioning  (Incl. Reliability Run) and COD