how to generate the ACWP forecast curve

No replies
M. Kamel Bessekri
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 2 Jul 2009
Posts: 27
Groups: None

Hi  Folks,

The acwp´s Data curve are provided form invoicing or Time sheet (from startdate to data date) , but how to generate  the forecast  curve of the  rest of acwp   between the  data date  and  a  estimated at completion ?

Is there any function which combine the cost variance and the performance cost index ?

Thanks

Kamel