Duration increase impacts my budgeted quantities

4 replies [Last post]
Luke Charet
User offline. Last seen 10 years 44 weeks ago. Offline
Joined: 25 Aug 2009
Posts: 18
Groups: None

Hi All,

I am having some issues with budgeted qtys/actual qtys/ remaining qtys.

My example is a simple one, I have an activity - Open Drain Lining. I have added a material resource and assigned a total qty of 710sqm. The task itself has now started and is now expected to take 2x a long. This is were my problem kicks in, my budgeted qty now increases and the actual/remainig units are out of whack. I have tried several activity types to no avail. I would love the budgeted qty to remain the same and the actual/remaining units total the budgeted qty no matter how long or short the activity duration is.

What I would like to see is even if the lining took 2 years it is still 710 and the remaining/actual is a product of the 710 based on % duraiton complete. This is playing having with my actuals complete and hence throwing out my % complete, overall progress.

Thanks heaps, just when you think you have P6 nailed you get more issues.

Replies

Christopher Hall
User offline. Last seen 11 years 31 weeks ago. Offline
Joined: 17 May 2012
Posts: 42
Groups: None

Luke, good to hear its sorted.

Luke Charet
User offline. Last seen 10 years 44 weeks ago. Offline
Joined: 25 Aug 2009
Posts: 18
Groups: None

Thanks Chris, works great. Im liking this planning planet, its an uphill battle learning yourself

Luke Charet
User offline. Last seen 10 years 44 weeks ago. Offline
Joined: 25 Aug 2009
Posts: 18
Groups: None

Thanks Chris, works great. Im liking this planning planet, its an uphill battle learning yourself

Christopher Hall
User offline. Last seen 11 years 31 weeks ago. Offline
Joined: 17 May 2012
Posts: 42
Groups: None

Luke, sounds like the things to check are;

  • duration type = fixed duration & units,
  • drive activity dates = unticked,
  • Option to 'recalculate acutals & cost when % complete changes' is ticked for project defaults under the resources assignments heading in the project / calculation tabs.

That should do it.  You'll need to re-work any activities you've started statussing after making the above changes.