Baseline Schedule/Provisional Package

No replies
Ariel Malibiran
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 6 Mar 2009
Posts: 54

Hi guys!

Can i call your great minds attention?

i have a schedule to be prepared with the following scenarios:

1. Package 1 has a duration of 2 years from NTP issue.

2. Package 2 may or may not be instructed to do so, however, if it will be included in the contract it will be advised within 6mos from the NTP of Package 1 and the duration for both Package 1 & 2 will be 3 years.

my questions are as follows:

a. am i going to prepare 2 schedules based on scenarios 1 & 2?

b. if i'll be making 1 schedule based on scenario 1 and will incorporate scenario 2 as an indicative program, and then later on Package 2 will not be included, my program will be incorrect due to  duration of Package 1 extended also upto 3 years.

 

Please advise on how to do it best with such condition..

 

Thanks & Best Regards,

 

Ariel