Adding steps Quickly

2 replies [Last post]
Joel Clark
User offline. Last seen 45 weeks 6 days ago. Offline
Joined: 19 Nov 2008
Posts: 9
Is there a way to add one step to each activity quickly through global change.....or....do I physically have to go to each activity and add one step?

Replies

Joel Clark
User offline. Last seen 45 weeks 6 days ago. Offline
Joined: 19 Nov 2008
Posts: 9
Arnold,

Very Nice! Thanks
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Joel,

You cannot add activity steps using global change. If some of your activities has the same step name then, select all these activities & assign activity steps using the "Steps" Command Bar Button located at the right corner of your screen. But first, create the Activity Step Templates.

Or you can copy the steps in one activity and paste it to other activity.

HTH.

Regards,