Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Pipe productivity rate

2 replies [Last post]
Anu Tor
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
Dear all,

Please tell me for piping productivity rate in DBI/day/welder as,
- Prefabrication
- Erection

Thanks,

Replies

Dilip Konar
User offline. Last seen 6 years 22 weeks ago. Offline
Joined: 5 Mar 2012
Posts: 5
Groups: None

i want to rate analysis of 2500mm dia pipe making with 20mm thickness Mild steel sheet. with material cost

Abhijit Kale
User offline. Last seen 5 years 32 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 126
Groups: None
Dear Anu,
The productivity depends upon the time cycle required for completing an activity.
time cycle depends upon, many factors,such as:
1.Diameter of Pipe.
2.Man power deployed
3.Equipemnt deployed.
4. Location and climateic conditions

you have given to little information in your querry.

At least mention the diameter of pipe.
cheers,