Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Float

5 replies [Last post]
Jaroslava Sedrlova
User offline. Last seen 17 years 47 weeks ago. Offline
Joined: 16 Apr 2005
Posts: 11
Groups: None
Hi.
I have little problem with understanding of differences between various types of float. Maybe somebody can help me.

Example: I have total float equal 10 and free float equal 5. The activity delays 7 days. 5 will not impact successors but 2 (over the free float) will. Is this right?

And what can you tell me about other types of float? I don’t need definition rather example.

Thank you
Jarka

Replies

Jaroslava Sedrlova
User offline. Last seen 17 years 47 weeks ago. Offline
Joined: 16 Apr 2005
Posts: 11
Groups: None
HI!
Thank you everybody.
It’s little bit clearer.
I’m just student. I have some result from MS Project and I want to know how it works in real word:)
Jarka
Larry Bjorn
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 4 Feb 2004
Posts: 59
Groups: None
Jaroslava,

Free float is the delay an activity can have without delaying a successor. Total float is the combined delay a chain of events can have without delaying the end date (end date being a specific fixed completion milestone).

Therefore, the result of activity Y being delayed by 7 days is that its Total float has been reduced by 7 days. You are right that 5 will not impact any successors but 2 will delay at least one successor X. Worth noting is that X does not necessary have the same total float as Y as X might be related to a second chain of event with a larger Total float.

Regards,
Larry
Anoon Iimos
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
float is refreshing during summer time...if you had established good relationships.

seriously, float only occurs because of dependencies, if there are no dependencies in your activities, each activity has its own completion date without any float at all.

It depends on how you define the relationships of your activities (pls. refer to the first paragraph). so if the relationships are incorrect, so is the float!
ersin namli
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 19 Jul 2005
Posts: 54
Groups: None
Hi, free float is the float between noncritical tasks. Total float is float between noncritical and critical task. Assume that we have 3 tasks A, B, and C. A and B are noncritical C is critical A is predecessor of B, B and C has finish to finish relation in this example A has total float but its free float is 0 but B has both free float and total float. we can understand here when A finishes B starts immediately if a delay occurs in activity A, this activity will use B’s float becouse A’s free float is 0 in other words it hasn’t got its own float. I hope it would be useful for you.
Andrew Sherwood
User offline. Last seen 17 years 41 weeks ago. Offline
Joined: 26 Mar 2007
Posts: 12
I would personally take the Free Float off of the columns, assuming you are using P3...

Total Float is the only thing worth looking at in my opinion...I have never used Free Float or seen it in any schedules I have ever worked...