AutoCad 2006

7 replies [Last post]
Marcio Sampaio
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Hello all PP members;

Do anyone have experience in the usage of Auto Cad 2006 as a tool to control projects (or small packages of a project)?

Regards.

Marcio Eduardo
Rio de Janeiro - Brazil

Replies

Marcio Sampaio
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
That is it Dayanidhi Dhandapany.

Thanks a lot.

Best Regards.
Dayanidhi Dhandapany
User offline. Last seen 3 years 4 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
you meant to say about VBA? Check their tutorials from autodesk.com website
Marcio Sampaio
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Thank u all for the responses.

Do u know where I can find material about this subject?

Regards.
Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Dear All

The use of AutoCAD (Drawing) integrate with project plan in planning is a way to illustrate sequency of works, identify progress, cause and effect. However, to have a proper planning and control and analysis, this integration can only act as and supporting tool. Still the primary tool is a details schedule. Things like comparsion to the baseline, identify time implication on CPM ...

I dont discount the use of Time Location diagram. However, it normally is very high level and have to associate with a physical element. For those invisible element, we still need to rely on the traditional schedule and planning tool

HTH

Alex
MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
AutoCAD 2006 can be used for both mentioned by VBA of AutoCAD.
Dayanidhi Dhandapany
User offline. Last seen 3 years 4 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
You can use it for drawing Time-Chainage Digarams and link the autocad drawing layout profile to display Start and Finish Dates from P3 using VBA. I heard about it.
MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
control which area? Progress or others?