Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Schedule Variance Procedures

2 replies [Last post]
Dana Fitkowski
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 17 Aug 2006
Posts: 4
Groups: None
Hello!

I was wondering if anyone was able to help, our group is looking for any info on writing a procedure for schedule variance reporting. Any examples or samples would be much appreciated.

Replies

Dana Fitkowski
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 17 Aug 2006
Posts: 4
Groups: None
Thanks very much Peter, certainly does help us out.
Peter Holroyd
User offline. Last seen 4 days 13 hours ago. Offline
Joined: 6 Jun 2005
Posts: 160
key data to be derived from the schedule is

1 SPI performance on an accum and period basis of current v baseline programmes - this gives the history then look forward by
2 SPI Index to Completion - this is the improvement required to finish the job on time (assuming you are behind)from which you can see whether it is realistic
3 Print out the top (5 ?) critical paths on the project and make sure they are sensible and everyone knows which are the current activitites on these critical paths
4 then as a test to see if you programme is getting more critical try a Float Trend Analysis graph
5 a simple Principle line would be nice but most software doesn’t support this

Hope this helps