Mitigation Plan - Baseline Adjustment

No replies
Selcan Gulec
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 8 Apr 2014
Posts: 2
Groups: None

Hi Everyone,

I am working as a delegate of the Employer on the construction project. As a planning engineer, my main responsibility is to lead the main contractor in preparing, updating, and revising their schedule. In addition to using P6, we were requested to use MS Project for a separate schedule that is not resource-loaded. Since the main contractor significantly fell behind their durations/dates, they were requested to prepare a mitigation plan. As a result, we received an adjusted plan without changing the completion date of the schedule. My question will be based on the table below.

Task NameFinish

BL1

Finish

BL2

Finish

Start

BL2

Start

BL1 Start

BL2 

Duration

BL1

Duration

Activity-A11 May '2401 Mar '2411 May '2414 Mar '2414 Mar '2401 Mar '241d1d

I would like to ask whether, if an activity has been completed before or during the mitigation preparation process, its baseline should be equal to BL1 or BL2? I believe that the baseline of the completed tasks should remain as BL1, and the remaining tasks should be updated to the new baseline (BL2).

Normally, I would advise splitting the in-progress activities and inserting a new one to mitigate the remaining works in the new plan. However, the project is fast-paced, and it may take longer to do so.