Re: HELP ON GLOBAL CHANGE

1 reply [Last post]
Tom Gouldburn
User offline. Last seen 11 years 1 week ago. Offline
Joined: 20 Aug 2012
Posts: 4
Groups: None

Hi Guys,

Hope all is well.

I'm new to p6 and have 3000 acitivites with incorect costing applied to activities

Would anyone be able to assist on helping me do a global change for removing budgeted cost/Actual cost ?

Thanks

Tom Gouldburn

Replies

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Tom

Can you not just delete the cost heads to clear them out and then add new ones.

That is what I would do in Asta Powerproject.

Best regards

Mike Testro