Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Generating Progress Curves in MS Excel

No replies
William Sargent
User offline. Last seen 17 years 1 week ago. Offline
Joined: 22 Jan 2007
Posts: 4
Groups: None
I’m looking to create a dynamic spreadsheet in MS Excel to double check P3 and do other work offline.

Specifically, I am looking to create a spreadsheet where I can enter in a total duration, remaining duration, a curve type and total number of units (manhours, euros, etc.) so that I may then be able to calculate the remaining values by period.

For example:

I have a ten month duration for manhours where durations are also in months. For this task I have allocated 100k manhours. I have chosen to model the based on a bell shaped distribution and have alocated the manhours as follows:

Month: qty
1: 1k
2: 3k
3: 8k
4: 15k
5: 23k
6: 23K
7: 15k
8: 8k
9: 3k
10: 1k

Halfway through the project, I progress the activity. I want to forecase the remaining distribution of 75K in accordance with the "trailing" end of the distribution curve which would yield the following values:

Month: qty
5: 23,630
6: 23,630
7: 15,411
8: 8,219
9: 3,081
10: 1,027

I can make these calculation manually, but as I stated above I’m looking for a MS Excel templete where I enter or select the appropriate variables and then view the result.

The curves that I am looking for a the standard curves in P3.

If anyone has any ideas, it would be greatly appreciated.

Cheers,