DCMA 14 Filter

No replies
Abbas Rajabpour
User offline. Last seen 45 weeks 2 days ago. Offline
Joined: 7 Oct 2022
Posts: 25
Groups: None

Hi everyone, 

Has anyone ever written formula for " DCMA 14"? 

 

If yes, can you share it please.

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

also in version 22.4 there is a tool in P6 its under view then check schedule its a list like the DCMA 14 point   

also look for a utility called xer reader it uses an xer file and performs the 14 point for you

Peter Holroyd
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 6 Jun 2005
Posts: 167

There's loads of P6 add ons that have this covered.