Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Importing an XER to a project - Data date?

No replies
Tom Turnham
User offline. Last seen 28 min 37 sec ago. Offline
Joined: 21 Aug 2013
Posts: 19
Groups: None

Hi Guys,

I wanted to copy some activities over from one project to another but I had to keep the activity IDs the same. The only way I could get that to work was to import the XER into the other project, which did work.

However, everytime I reschedule P6 acts as if I have 2 projects open and gives me the option to use each projects own data date or apply a selected data date to all projects.

Is there a way of getting P6 to think its just one project again?

Cheers,

Tom