Printing Calendars

2 replies [Last post]
Rodney Jones
User offline. Last seen 1 week 5 days ago. Offline
Joined: 17 Jun 2012
Posts: 43
Groups: None

Hi All,

 

Using P6 V20 Server based system. Can someone suggest how I can print a Calendar? As an example, I have a calendar that is 6 days per week, running for two years, how do I print the calendar for each month for that 2 year period?

 

Rod

Replies

Zoltan Palffy
User offline. Last seen 4 hours 21 min ago. Offline
Joined: 13 Jul 2009
Posts: 2990
Groups: None

get your hands on the xer reader its an excel file that reads an xer file 

Rodel Marasigan
User offline. Last seen 5 hours 55 min ago. Offline
Joined: 25 Oct 2006
Posts: 1639

Primavera does not have a function to Print Calendar. There are available 3rd party software such as toolkit that can print calendar. Alternatively, you can copy and paste screenshot of your calendar monthly to accomplished that task.