Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resources not showing on histogram

1 reply [Last post]
Philip James
User offline. Last seen 34 weeks 3 days ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None
Hi I've added resources to my level of effort bars (made more sense i thought, as you would have 1 gang complete x amount of activities), yet when I come to look at the histogram they don't appear? I never needed to do resource loading before, and this project is for studying. Kind Regards Philip

Replies

Zoltan Palffy
User offline. Last seen 4 days 3 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

of you use a a LOE type of activity then you MUST assign a resouce curve to that LOW activity or all of the resources wil stack up on the data date.

fro the LOE activity click onthe resource tab at the bottm 

then rigth click and select customize resource columns

expand the general category and select curve

then click in the curve box and select a curve teh standard curve is Linear

done