Resources not showing on histogram

1 reply [Last post]
Philip James
User offline. Last seen 2 years 9 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None
Hi I've added resources to my level of effort bars (made more sense i thought, as you would have 1 gang complete x amount of activities), yet when I come to look at the histogram they don't appear? I never needed to do resource loading before, and this project is for studying. Kind Regards Philip

Replies

Zoltan Palffy
User offline. Last seen 14 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

of you use a a LOE type of activity then you MUST assign a resouce curve to that LOW activity or all of the resources wil stack up on the data date.

fro the LOE activity click onthe resource tab at the bottm 

then rigth click and select customize resource columns

expand the general category and select curve

then click in the curve box and select a curve teh standard curve is Linear

done