Imported Project Without Baseline

2 replies [Last post]
irfan morkoc
User offline. Last seen 1 week 3 days ago. Offline
Joined: 8 Mar 2013
Posts: 8
Groups: None

Hi,

I have imported a file without its baseline. But I see baseline start/finishes dates are different than project start/finish dates. I checked there is no assigned baseline. I expect if there is no baseline assigned to the project then baseline dates should be equal to project dates.

Could you please explain ?

Regards

Replies

irfan morkoc
User offline. Last seen 1 week 3 days ago. Offline
Joined: 8 Mar 2013
Posts: 8
Groups: None

Thank you very much Alexandre.

Alexandre Faulx-B...
User offline. Last seen 56 min 52 sec ago. Offline
Joined: 20 Jan 2003
Posts: 1325

Hi Irfan,

Insert the Planned Start and Planned Finish dates in the gantt chart columns; you should find that these dates are different from Early Start / Finish dates, and the same as Baseline ones.

When a project has no baseline, planned dates are used instead.

Years ago, the P6 guru Ron Winter had published a very interesting paper "Understanding P6 dates"; easy to find on the Internet, as I do not know how to share my local file on the forum

Alexandre