Forum Sponsor:

Portfolio Planner is software which improves portfolio, project and resource management.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Showing productivity changes with different Resource Calendars

5 replies [Last post]
Dejan Kezic
User offline. Last seen 1 week 3 days ago. Offline
Joined: 21 Mar 2018
Posts: 4
Groups: None

Hi everyone, I am kindly asking for help about following problem.

I need to show lower productivity per several resources in my schedule in winter period. Those resources are commodities.

Other resources (manpower and equipment) as well as activities should be intacted.

So my idea was that I will keep on using original project calendar (7 days x 10 hours) for activities and mapower/equipment resources, and modified calendar (summer months 7 days x 10 hours and winter months 6 days x 6 hours)  for a.m. commodity resources.

Unfortunately it did not show any difference from original schedule and all resources were distributed lineary.

Is there some solution how to get this result?

Thank you!

PS

I should mention that I have changed to different clandar for all activities and it did show changes (higer resources in summer and lower resources in winter), but it does not help me because I don't want to show changes for manpower and equipment (only for commodities).

Also, I know that creating more detailed schedule with activities dedicated to volume of work for winter months will solve problem, but I don't have time and need fast solution.

Replies

Rafael Davila
User offline. Last seen 9 hours 7 min ago. Offline
Joined: 1 Mar 2004
Posts: 4864

Please click the following link to download presentation pdf.

Link to Quantities_Workloads_and_Production_Rates.pdf/file

Best Regard,

Rafael Davila

Rafael Davila
User offline. Last seen 9 hours 7 min ago. Offline
Joined: 1 Mar 2004
Posts: 4864

Dejan:

How do you show productivities in P6 in a transparent way? Where do you enter such values? As far as I recal there is no such functionality in P6?

What do you mean by activities dedicated to volume of work for winter?

Activity might be delayed from winter to summer. And what when a portion falls in winter and another portion fall in summer, this make too many possibilities. Using separate activities may not be a good idea.

Best Regards

Rafael

Raymund de Laza
User offline. Last seen 1 week 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 744

Use the REsource Detail: Effectivity and Max Unit per Time

Set the Reduced Max Qty (Max Unit per Time) within the Effective dates.

Rafael Davila
User offline. Last seen 9 hours 7 min ago. Offline
Joined: 1 Mar 2004
Posts: 4864

Zoltan Palffy
User offline. Last seen 20 hours 5 min ago. Offline
Joined: 13 Jul 2009
Posts: 2683
Groups: None

put the resources on a different calendar